Project Status

 
 
 

        

Land Required land for the project has been acquired.

Water We have received no objection letter from CGWB Govt. of India for use of ground water for construction need.Moreover our application for getting water from River Birupa has already been considered by the water allocation committee, Govt of Orissa.

Coal: - Our application for coal linkage is pending with the ministry of coal after being recommended by the Central Electricity Authority and Ministry of Power. We are eligible for 100% coal linkage. However, as an alternative arrangement, we have entered into contracts with private coal suppliers/washeries for supply of washery rejects and washed coal.

Environmental Clearance - State Pollution Control Board Orissa has already issued terms of reference in our favour for conducting Environment Impact Assessment Study for which we had appointed consultant to study the same. The EIA/EMP study for the project has already been completed. Public hearing has been scheduled.

System Study for the grid connectivity has been completed by OPTCL.

Power evacuation system report has been prepared.

Civil aviation clearance has already been obtained from ARC, Charbatia relating to Chimney height.

Contract has already been awarded for switchyard and transmission line net work.

Generator Transformer & Station auxiliary transformer order has already been placed with AREVA T & D.

Construction Power for 750 KVA has already been approved by CESU & yet to be energized.

EPC Contract for chimney has already been awarded to M/s Bygging India Limited.

Civil Construction contract has already been awarded to M/s Sri Durga Condev (P) Ltd.

 